Figure 1: OC Curve of Single Sampling Plan n=50 and a=1
An OC curve is generally summarized by two points on the curve: the acceptable quality level (AQL) and the lot tolerance percent defective (LTPD). The AQL describes what the sampling plan generally accepts; formally, it is that percent defective with a 95% percent chance of acceptance. The LTPD, which describes what the sampling plan generally rejects, is that percent defective with a 10% chance of acceptance. As shown in Figure 2, the single sampling plan n=50 and a=1 has an AQL of 0.72% defective and an LTPD of 7.6%. The sampling plan routinely accepts lots that are 0.72% or better and rejects lots that are 7.6% defective or worse. Lots that are between 0.72% and 7.6% defective are sometimes accepted and sometimes rejected.Figure 2: AQL and LTPD of Single Sampling Plan n=50 and a=1
Manufacturers must know and document the AQLs and LTPDs of the sampling plans used for their products. The AQLs and LTPDs of individual sampling plans can be found in Table X of MIL-STD-105E, and Chart XV of ANSI Z1.4 gives the AQLs and LTPDs of entire switching systems (described below).1,2 Software also can be used to obtain the AQLs and LTPDs of a variety of sampling plans.6 SELECTING STATISTICALLY VALID SAMPLING PLANS Documenting the protection provided by your company’s sampling plans is only half the job. You must also provide justification for the AQLs and LTPDs used. This requires that the purpose of each inspection be clearly defined. Depending on past history and other circumstances, sampling plans can be used for a variety of purposes. In the examples described below, an AQL of 1.0% is specified for inspections for major defects. The AQL given in this specification is not necessarily equal to the sampling plan AQL, and so it will be referred to as Spec-AQL to make this distinction clear. Spec-AQLs are commonly interpreted as the maximum percent defective for which acceptance is desired. Lots below the Spec-AQL are best accepted; Lots above the Spec-AQL are best rejected. The Spec-AQL, therefore, represents the break-even quality between acceptance and rejection. For lots with percent defectives below the Spec-AQL, the cost of performing a 100% inspection will exceed the benefits of doing so in terms of fewer defects released. Since this cost is ultimately passed on to the customer, it is not in the customer’s best interest for the manufacturer to spend $1000 to 100% inspect a lot if only one defect is found that otherwise would have cost the customer $100. Spec-AQLs should not be interpreted as permission to produce defects; however, once lots have been produced, the Spec-AQLs provide guidance on making product disposition decisions. Example 1: If a process is known to consistently produce lots with percent defectives above the Spec-AQL, all lots should be 100% inspected, but if some lots are below the Spec-AQL, the company could use a sampling plan to screen out lots not requiring 100% inspection. To ensure that lots worse than the Spec-AQL are rejected, a sampling plan with an LTPD equal to the Spec-AQL can be used, but at the risk of rejecting some acceptable lots. For a Spec-AQL of 1.0%, the single sampling plan n=230 and a=0, which has an LTPD of 1.0%, would be appropriate. There is a simple formula for determining the sample size for such studies. Assuming an accept number of zero and the desired confidence level of 90%, the required sample size is:n = 230/Spec-AQL
For 95% confidence, the formula isn = 300/Spec-AQL
Example 2: The same sampling plan might also be used to validate a process for which there is no prior history. Before reduced levels of inspection are implemented, it should be demonstrated that the process regularly produces lots below the Spec-AQL. If the first three lots pass inspections using a sampling plan with an LTPD equal to the Spec-AQL of 1.0%, the manufacturer can state with 90% confidence that each of these lots is <1% defective. However, other sampling plans might be better choices. Suppose the process is expected to yield lots that are around 0.2% defective. The sampling plan n=230 and a=0 has an AQL of 0.022% and therefore runs a sizeable risk of failing the validation procedure. A sampling plan with an AQL of 0.2% and an LTPD of 1% would be a better choice. Using the software cited earlier, the resulting plan is n=667 and a=3.3 Example 3: Once it has been established that the process consistently produces lots with percent defectives below the Spec-AQL, the objective of future inspections might be to ensure that lots with >=4% defective are not released. This requires a sampling plan with an LTPD of 4%. Because the sampling plan should also ensure that lots below the Spec-AQL are released, the plan’s AQL should be equal to the Spec-AQL. According to Table I from the book Guide to Acceptance Sampling3, which gives a variety of sampling plans indexed by their AQLs and LTPDs, the single sampling plan n=200 and a=4 is the closest match. It has an LTPD of 3.96% and an AQL of 0.990%, and thus is statistically valid for this purpose. Example 4: Now suppose that the process has run for 6 months with an average yield of 0.1% defectives and no major problems. Although the process has a good history, there is still some concern that something could go wrong; as a result, the manufacturer should continue to inspect a small number of samples from each lot. For example, a sampling plan might be selected that ensures that a major process failure resulting in ≥20% defective will be detected on the first lot. The sampling data can then be trended to detect smaller changes over extended periods of time. When selecting a sampling plan to detect a major process failure, the nature of the potential failure modes should be considered. If the primary failure mode of concern is a clogged filter and past failures have resulted in ≥20% defectives, the single sampling plan n=13 and a=0, which has an LTPD of 16.2% and an AQL of 0.4% in Table I3, is statistically valid. If the potential failure mode of concern is a failure to add detergent to the wash cycle, with a resulting failure rate of 100%, the single sampling plan n=1 and a=0 is valid.Table I: Single Sampling Plans Indexed by AQL and LTPD3
AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL | Approximate Ratio of LTPD/AQL |
---|---|---|---|---|---|---|---|---|---|
45 | 11 | 6.5 | 5 | 4 | 3.2 | 2.8 | 2.3 | 2 | |
10% | – | ||||||||
6.5% | – | ||||||||
4.0% | – | ||||||||
2.5% | |||||||||
1.5% | |||||||||
1.0% | |||||||||
0.65% | |||||||||
0.4% | – | ||||||||
0.25% | – | – | |||||||
0.15% | – | – | – | ||||||
0.1% | – | – | – | – | |||||
0.065% | – | – | – | – | – | ||||
0.04% | – | – | – | – | – | – | |||
0.025% | – | – | – | – | – | – | – | ||
0.015% | – | – | – | – | – | – | – | ||
0.01% | – | – | – | – | – | – | – | – | |
0.0065% | – | – | – | – | – | – | – | – | |
0.004% | – | – | – | – | – | – | – | – | |
0.0025% | – | – | – | – | – | – | – | – |
This standard is intended to be used as a system employing tightened, normal, and reduced inspection on a continuing series of lots …. Occasionally specific individual plans are selected from the standard and used without the switching rules. This is not the intended application of the ANSI Z1.4 system and its use in this way should not be referred to as inspection under ANSI Z1.4.2
Several companies have received Form 483s from FDA for not using the switching rules, a problem that could have been avoided by having written procedures specifying that the switching rules are not used. When is the use of switching rules appropriate and when should individual sampling plans be selected instead? Z1.4 was developed specifically to induce suppliers “to maintain a process average at least as good as the specified AQL while at the same time providing an upper limit on the consideration of the consumer’s risk of accepting occasional poor lots.”2 Thus, the Z1.4 switching system should not be used to inspect isolated lots, nor should they be used to specify the level of protection for individual lots. In those cases individual plans should be selected instead. One situation warrants special mention. Acceptance sampling is frequently used for processes that generally produce good product but might on occasion break down and produce high levels of defects. If protection against isolated bad lots or the first bad lot following a series of good lots is the key concern, the Z1.4 switching rules should not be used or, if they are, the reduced inspection should be omitted. Because the Z1.4 switching rules are designed to react to gradual shifts in the process average, they frequently fail to detect isolated bad lots and do not react quickly to sudden shifts in the lot quality. Even when appropriate, the Z1.4 switching rules are complicated to apply. However, quick switching systems have been developed that are both simpler to use and provide better protection during periods of changing quality.3 Finally, there are two common misconceptions about Z1.4. Many people believe that the required sample sizes increase for larger lots because more samples are required from such lots to maintain the desired level of protection. The truth is that the standard specifies larger sample sizes to increase the protection provided for larger lots. The reason for this increase is based on economics: It is more expensive to make errors classifying large lots; as a result, Z1.4 requires more samples from larger lots to reduce the risk of such errors. To maintain the same level of protection, one can simply select a sampling plan based on its OC curve and then use this plan for all lots regardless of size. The single sampling plan n=13 and a=0 provides the same protection for a lot of 200 units as for a lot of 200,000 units.3,4 The second misconception is that use of Z1.4 ensures that lots worse than the AQL are rejected. According to this misconception, if the AQL is 1%, lots with >1% defectives are routinely rejected. The truth is that there is a sizable risk of releasing such lots–one sampling plan with an AQL of 1% accepts lots that are <=16% defective. The protection provided by the sampling plan is determined by its LTPD, not AQL, which reveals nothing about what a sampling plan will reject. As a result of this misconception, many manufacturers believe that their sampling plans provide greater protection than they do. This illusion can lead to the use of inappropriate sampling plans and can provide a false sense of security. Repeating the advice given earlier, manufacturers should determine and document the actual AQLs and LTPDs of all their sampling plans. While Z1.4 and equivalent standards are widely used by the device industry, rarely are they used in the manner intended. Most commonly, individuals sampling plans are selected from them. Other tables are better suited for this purpose, and companies should not be afraid to switch to using those tables. In addition, using Z1.4 does not ensure valid sampling plans and, in fact, can complicate the selection process. SPC VERSUS ACCEPTANCE SAMPLING? Much has been written about the greater benefits to be achieved by using SPC as opposed to acceptance sampling. But although preventing defects is certainly more desirable than detecting them through inspection, SPC does not eliminate the need for acceptance sampling. As indicated in Table II, there are fundamental differences between the two techniques. In SPC, control charts are used to make process control and process improvement decisions, and actions are taken on the process to ensure that future products are good. In contrast, sampling plans are used to make product disposition decisions, and actions are taken on previously produced lots to ensure the quality of released product. Ideally, with SPC in place no defectives will ever be made and acceptance sampling will become unnecessary: in practice, however, all processes have some risk of failure, and thus some procedure for accepting and rejecting product is generally required.Table II: Differences Between Control Charts and Sampling Plans
Control Chart | Sampling Plan | |
---|---|---|
Decision | Adjust or Leave Alone | Accept or Reject |
Act On | Process | Product |
Focus | Future Product | Past Product |
Figure 3: Acceptance Control Chart
If attributes sampling is performed, the data must be handled much differently, and care must be taken in implementing SPC so that the resulting change is not illusionary. Consider, for example, a packing operation that inspects for missing parts using the single sampling plan n=13 and a=0. Whenever a lot is rejected, an attempt is made to fix the process. Historically, the process has averaged around 0.2% defective. When management decides to implement SPC, a p-chart of the inspection data is constructed as shown in Figure 4. The upper control limit is 3.92%, and samples with one or more defectives exceed this control limit, triggering attempts to fix the process and rejection of recent product. The company can now state truthfully that SPC is used, but in reality nothing has changed–the same data are collected and the same actions taken. A better approach is to continue acceptance sampling as before and, because this does not protect against a gradual increase in the process average, to analyze the resulting data for trends. Figure 5 shows a p-chart of the same data, but with the data from each day combined. This chart indicates that a change occurred between days 5 and 6; this change is not so apparent in Figure 4. Neither SPC or acceptance testing can detect a problem before defectives are produced. However, by accumulating data over time, attribute control charts can indicate small changes in the process average that acceptance sampling will not reveal. Used in combination, sampling plans provide immediately protection against major failures while control charts protect against minor sustained problems.Figure 4: p-Chart of Inspection Results
Figure 5: Daily p-Chart
REDUCING INSPECTION COSTS Two sampling plans can have the same AQL and LTPD and nearly equivalent OC curves. When they are followed, the same percentage of good lots will be accepted and the same percentage of bad lots rejected. The quality of the products released to customers will be the same, as will the reject and scrap rates. From a regulatory point of view, the two sampling plans are substantially equivalent. However, one of these plans may be less costly to use. Consider an example. The ANSI Guideline for Gamma Sterilization5 provides procedures for establishing and monitoring radiation dosages. One procedure is a quarterly audit of the dosage that requires the sterilization of test units at a lower dosage than is actually used for the product. The test dose is selected to give an expected positive rate of 1%. (A positive is a unit that tests nonsterile.) For each audit, an initial sample of 100 units is tested. If two or fewer positives are found, the process has passed the audit; in the event of three or four positives, one retest can be performed. This quarterly audit procedure has an AQL of 1.50% and an LTPD of 5.55%. An alternative to this procedure is to test 50 samples, passing on zero positives and failing on four or more positives. In the event of 1 to 3 positives, a second sample of 100 units is tested. The audit is considered passed only if the cumulative number of positives in the 150 units is four or less. This double sampling plan has an AQL of 1.36% and LTPD of 5.73%.Figure 6: OC Curves of the ANSI Quarterly Audit Sampling Plan and an Alternative Plan for Monitoring Sterilization Dosage
The OC curves of both procedures are nearly identical, as shown in Figure 6. Indeed, these two sampling plans are substantially equivalent procedures, except for the number of units tested. Figure 7 shows average sample number (ASN) curves for the two plans. If the positive rate is 0.5%, the alternative procedure requires an average of 70 units compared to an average of 102 for the ANSI quarterly audit procedure. If the alternative plan is used to destructively test expensive medical devices, this difference can mean a sizable savings.Figure 7: ASN Curves of Audit Sampling Plan and Alternative
CONCLUSION Acceptance sampling is one of the oldest techniques used for quality control, yet it remains poorly understood and misconceptions regarding its procedures and terminology are widely held. Acceptance sampling does not have to be complicated. Your company can optimize its procedures by remembering this list of principles:- The protection level provided by a sampling plan is described by what it accepts — its AQL–and what it rejects– its LTPD.
- Selecting a statistically valid sampling plan requires stating the objective of the inspection, selecting the appropriate AQL and LTPD, and then choosing a sampling plan that provides the desired protection.
- Companies must know the AQLs and LTPDs of all their sampling plans. It doesn’t matter whether a sampling plan comes from MIL-STD-105E or some other source, and the protection provided by a plan does not depend on the lot size; it’s the AQL and LTPD that reveal what protection the sampling plan provides.
- SPC cannot serve as a replacement for acceptance sampling. Instead, these two techniques should be combined by using the same data to control the process and to make product disposition decisions.
- Sampling plans with the same AQL and LTPD are substantially equivalent procedures, so costs can sometimes be reduced by using equivalent double, multiple, or variables sampling plans as alternatives to single sampling plans.
- Sampling Procedures and Tables for Inspection by Attributes, MIL-STD-105E, Washington D.C. , U.S. Government Printing Office, 1989 .
- Sampling Procedures and Tables for Inspection by Attributes, ANSI/ASQC Z1.4, Milwaukee, WI, American Society for Quality Control, 1981.
- Taylor, W A, Guide to Acceptance Sampling, Libertyville, IL, Taylor Enterprises, 1992. (Software is supplied with this book.)
- Schilling, E G, Acceptance Sampling in Quality Control, New York City, Marcel Dekker, 1982.
- Guideline for Gamma Radiation Sterilization, ANSI/AAMI ST32-1991, Arlington, VA, Association for the Advancement of Medical Instrumentation, 1992.
- Sampling Plan Analyzer, Taylor Enterprises, Inc., Variation.com/spa.
Appeared in MDDI (Medical Device & Diagnostic Industry), Oct. 1995, p. 92-108, Canon Communications
(Used by FDA in new inspector training)
Copyright © 1995 Taylor Enterprises, Inc.
Further information can be found in:
- Book Guide to Acceptance Sampling
- STAT-09, Manufacturing Acceptance Sampling Plans and Inspections, of the book Statistical Procedures for the Medical Device Industry
- STAT-10, Statistical Techniques for Trending Data, of the book Statistical Procedures for the Medical Device Industry
- Software Sampling Plan Analyzer
- Acceptance Sampling Standards page